518 Permits Filed, 10% Under Construction: The Real Story

9 min read

Vancouver's multiplex boom looks different from the ground. Here's what 518 permit applications, 98% lot failure rates, and new concurrent processing actually mean for your property.

Key takeaway

Vancouver multiplex market analysis revealing the gap between permits (518 filed) and actual construction (10-15%).

Covers why 98% of lots don't pencil financially, the new concurrent DP/BP processing for 4-unit projects, Bill 25 enforcement implications, and the strategic shift from build-and-hold to build-and-sell models.

What this covers

  • permit vs construction gap
  • concurrent processing stream
  • Bill 25 enforcement
  • build-and-sell strategy
  • lot frontage requirements
  • BC Hydro PMT costs
vancouver multiplex-permits bill-44 bill-25 market-update 2026

518 multiplex applications filed in Vancouver by end of 2025. Only 10-15% are under construction. The gap between permits and shovels in the ground tells the real story of Vancouver’s multiplex market right now—and it’s not the one you’ve been reading in headlines.

The 518 Number Everyone Gets Wrong

Let’s be direct about what Vancouver’s 518 multiplex applications actually mean. City staff will tell you it’s a success story. Developers know the reality: roughly 40% are approved, but most remain paper projects.

The math on “build-and-hold” broke in 2025. Interest rates murdered rental economics. The homeowners who thought they’d build a fourplex and retire on rental income? Most discovered their proformas didn’t survive contact with actual financing terms.

Application StatusPercentageCount (Approx)
Under Construction10-15%~50-70
Approved (not started)25-30%~120-140
In Review40-50%~190-230
Withdrawn/Denied~15%~70

Why 98% of Lots Don’t Pencil

VanPlex has analyzed over 86,000 R1-1 lots in Vancouver. The uncomfortable truth: 98% don’t make financial sense for the average homeowner attempting a DIY build-and-hold strategy.

Here’s what kills most projects:

Lot frontage under 33 feet. The fixed costs of stairwells, setbacks, and building code compliance eat the same square footage whether you’re building on a 33-foot lot or a 50-foot lot. On narrow lots, you’re left with units too small to command premium prices.

BC Hydro PMT requirements. This one blindsided dozens of 2025 projects. Many multiplexes now require on-site transformers (pad-mounted transformers). These eat up a parking spot or garden space and add $40,000-$80,000 to your budget. Check your electrical requirements early—it’s a project killer.

Construction costs at $400-500/sqft. Hard costs haven’t budged despite rate cuts. A 3,500 sqft fourplex runs $1.4-1.75M in construction alone before soft costs.

The Concurrent Processing Breakthrough

Vancouver announced one genuinely useful change for 2026: concurrent Development Permit and Building Permit processing for projects up to 4 units.

Previously, you’d wait 6-12 months for DP approval, then start the BP process. Now eligible projects can run both reviews simultaneously. Real-world impact: potentially 4-6 months saved on the critical path.

Who qualifies:

  • Maximum 4 units (2 units per building)
  • Standard lot sizes (under 1,000 m²)
  • Projects following the small-site rainwater management pathway

If you’re considering a 5-6 unit project, you’re still looking at 12-18 month processing delays. The concurrent stream is specifically for simpler builds.

Bill 25: The Enforcement Hammer Drops

Some municipalities thought they’d comply with Bill 44 on paper while making projects unbuildable through creative bylaw obstruction. Impossible parking requirements. Extreme setbacks. The province noticed.

Bill 25 (passed late 2025) gives BC Housing authority to override these local restrictions. Municipalities that technically complied but practically obstructed now face provincial intervention.

What this means for homeowners: if your city has been slow-walking multiplex approvals, expect the process to speed up. The political cover for obstruction is gone.

The 2026 Market Reality: Build-and-Sell Dominates

Here’s the strategic shift every Vancouver homeowner needs to understand: “build-and-hold” is largely dead for 2026. The viable model is “build-and-sell” (strata).

Strategy2025 Viability2026 ViabilityWhy
Build & Hold (rental)PoorPoorInterest rates kill cash flow math
Build & Sell (strata)ModerateStrongBuyer demand + lower carrying costs
Partner DevelopmentStrongStrongRisk sharing + expertise access
Sell to DeveloperModerateStrongPremium for permitted lots

The sweet spots for 2026:

  • 4-plex and 5-plex projects on lots with 49.5ft+ frontage
  • 3-bedroom units targeting families priced out of detached homes
  • Transit-adjacent locations within 400m of frequent service

What’s Actually Getting Built

Walk through Renfrew-Collingwood or Kensington-Cedar Cottage and you’ll see the pattern. The multiplexes moving forward share common DNA:

Lot characteristics:

  • 49.5-50+ foot frontage
  • At least 5,000 sqft lot area
  • R1-1 zoning (or equivalent SSMUH eligible)
  • No heritage designation complications

Unit mix:

  • 3-bedroom units at 1,000-1,200 sqft predominate
  • Targeting $900K-$1.2M price points
  • Families, not investors, as primary buyers

Developer profile:

  • Experienced builders with capital access
  • Pre-sale capacity to satisfy lender requirements
  • Relationships with efficient trades

The Rainwater Management Curveball

Vancouver’s new rainwater management requirements (effective July 2025) added another compliance layer. Every multiplex now needs detention systems.

The good news: the “Small Site Pathway” exempts standard lots from full engineering requirements. If you’re under 1,000 m² and following prescriptive standards, you avoid weeks of drainage engineering work.

The bad news: if you’re on a larger lot or have unusual conditions, budget $15,000-$30,000 and 4-8 weeks for the drainage engineering and review process.

Three Moves for 2026

Based on current market data, here’s what makes sense for Vancouver homeowners considering multiplex development:

1. Check your frontage first. If you’re under 33 feet, the economics are brutal. Above 49.5 feet is the sweet spot. Between those numbers—it depends on the specific lot geometry.

2. Verify BC Hydro requirements early. Before you spend $50K on design, find out if you need a PMT. This single factor has killed more 2025 projects than any zoning issue.

3. Design for the concurrent stream. If you can make a 4-unit project work, you avoid months of permit delay. Only go to 5-6 units if the math demands it.

Prefab and Modular: The 2026 Experiment

Watch for modular multiplex projects in 2026. Several BC manufacturers are targeting the market with factory-built units promising:

  • 30-40% reduction in on-site construction time
  • Better cost predictability
  • Quality control advantages

Early projects are still proving the model. If modular delivers on promises, it could shift the economics meaningfully by late 2026.

How to Know If Your Property Works

The gap between “eligible under Bill 44” and “profitable to develop” is massive. Eligibility is easy—profitability requires analysis.

VanPlex’s PlexRank™ system evaluates the factors that actually determine development success:

  • Lot geometry and buildable area
  • Current and projected land values
  • Construction cost estimates for your specific site
  • Rental income potential vs. strata sale values
  • Timeline and carrying cost projections

Visit VanPlex.ca to check your property’s development potential. We’ve analyzed 86,000+ Vancouver lots—chances are yours is already in our database.


David Babakaiff, CEO & Co-Founder of VanPlex

PlexRank™ | Profit with Multiplex

Frequently asked questions

How many of Vancouver's 518 multiplex applications are actually under construction?

Only 10 to 15 percent, roughly 50 to 70 of the 518 multiplex applications filed in Vancouver by the end of 2025, are under construction. Another 25 to 30 percent are approved but not yet started, 40 to 50 percent remain in review, and about 15 percent have been withdrawn or denied, meaning the headline permit count overstates how much building is actually happening on the ground.

Why do 98% of Vancouver R1-1 lots not make financial sense for multiplex development?

VanPlex analyzed over 86,000 R1-1 lots in Vancouver and found that 98 percent do not pencil financially for the average homeowner attempting a do-it-yourself build-and-hold strategy. The main culprits are lot frontage under 33 feet (which leaves units too small to command premium prices), BC Hydro pad-mounted transformer requirements that can add $40,000 to $80,000 to a budget, and construction costs of $400 to $500 per square foot that have not fallen despite interest rate cuts.

What is Vancouver's new concurrent Development Permit and Building Permit processing?

Starting in 2026, Vancouver allows Development Permit and Building Permit reviews to run simultaneously for projects up to 4 units, rather than waiting 6 to 12 months for Development Permit approval before starting the Building Permit process. This can save 4 to 6 months on the critical path, but it only applies to projects with a maximum of 4 units (2 units per building), standard lot sizes under 1,000 square metres, and projects following the small-site rainwater management pathway.

What does Bill 25 do to municipalities that slow-walk multiplex approvals?

Bill 25, passed in late 2025, gives BC Housing authority to override local restrictions from municipalities that technically complied with Bill 44 on paper but made projects unbuildable through obstacles like impossible parking requirements or extreme setbacks. For homeowners in a city that has been slow-walking multiplex approvals, the post frames Bill 25 as removing the political cover for that kind of obstruction.

Is build-and-hold or build-and-sell the better multiplex strategy in Vancouver for 2026?

The post argues build-and-sell (strata) is the stronger strategy for 2026, since build-and-hold rental economics were killed by interest rates that make the cash flow math poor in both 2025 and 2026. Build-and-sell moved from moderate viability in 2025 to strong in 2026 due to buyer demand and lower carrying costs, and selling the permitted lot directly to a developer also improved from moderate to strong for the same reason.

What lot frontage works best for a Vancouver multiplex in 2026?

The post recommends checking frontage first: lots under 33 feet face brutal economics because fixed costs for stairwells and setbacks consume the same square footage regardless of lot width, while lots above 49.5 feet hit the sweet spot for 4-plex and 5-plex projects. Lots between those two figures depend on the specific lot geometry rather than following a simple rule.

What new rainwater management rule affects Vancouver multiplex projects?

Vancouver's rainwater management requirements, effective July 2025, require every multiplex to include detention systems. Standard lots under 1,000 square metres following prescriptive standards qualify for the Small Site Pathway, which exempts them from full engineering requirements, while larger or unusual lots require $15,000 to $30,000 and 4 to 8 weeks for drainage engineering and review.

What unit type is actually getting built in Vancouver multiplexes right now?

The multiplexes moving forward typically sit on lots with 49.5 to 50 feet or more of frontage and at least 5,000 square feet of lot area with R1-1 or equivalent SSMUH-eligible zoning and no heritage complications. The predominant unit type is 3-bedroom units at 1,000 to 1,200 square feet, priced at $900,000 to $1.2 million and targeting families rather than investors as the primary buyer.

Free 12-page guide for Vancouver-area homeowners. Build, sell, hold, or partner — side-by-side comparison of the numbers, timeline, and risk on each path.

Verified phone required. We'll text you the link in 60 seconds.

David Babakaiff

David Babakaiff

Co-Founder, VanPlex | 25+ Years BC Construction

David Babakaiff is Co-Founder of VanPlex with 25+ years scaling BC construction. He led Alair Homes Vancouver to the 2024 HAVAN Award for Best Multiplex Unit in the GVRD. VanPlex’s PlexRank™ algorithm scores residential parcels across BC for multiplex conversion potential under Bill 44.